A UK-compliant Risk Assessment & Method Statement pre-filled for scaffolders. Edit the details for your site, then print or save as PDF.

Risk Assessment & Method Statement

Trade: Scaffolders · Generated 17/07/2026

1. Scope of works

Erection, alteration and dismantle of tube-and-fitting or system scaffold to TG20:21 / SG4:22.

2. Method statement

  1. Site induction and RAMS briefing signed by all operatives before work starts.
  2. Set up welfare, first-aid kit and fire point. Confirm nearest A&E.
  3. scaffolders team collects materials from designated laydown area — no interference with other trades' zones.
  4. Isolate, lock off and prove dead any services (electric, gas, water) in the work zone.
  5. Carry out task in accordance with method statement and manufacturer instructions.
  6. Housekeeping at end of each shift — waste segregated, walkways clear, tools tethered or stored.
  7. End-of-day sign-off with photo evidence uploaded to project record.

3. Hazards, persons at risk & control measures

HazardWho is at riskControl measures
Falls during erection/dismantleScaffoldersAdvance guardrail system. Harness clipped to scaffold tube during lifts.
Falling componentsPublic, site crewExclusion zone, banksman, no throwing tubes/boards.
Overhead power linesScaffoldersGS6 clearance. DNO consulted if within 6m of LV / 15m of HV lines.
Manual handling — tubes, boards, fittingsScaffoldersTwo-person handling of >6m tubes. Rest breaks.

4. PPE required

  • Safety helmet (EN 397)
  • Safety footwear (EN ISO 20345, S3 minimum)
  • Hi-vis vest (EN ISO 20471, class 2)
  • Impact gloves (EN 388)
  • Safety glasses (EN 166)
  • Full-body harness with shock-absorbing lanyard (EN 361/355)

5. Legislation & guidance

  • Health and Safety at Work Act 1974
  • Construction (Design and Management) Regulations 2015
  • Management of Health and Safety at Work Regulations 1999
  • Work at Height Regulations 2005
  • PUWER 1998

6. Approval

Prepared by (competent person)
Name / signature / date
Approved by (principal contractor)
Name / signature / date