A UK-compliant Risk Assessment & Method Statement pre-filled for electricians. Edit the details for your site, then print or save as PDF.

Risk Assessment & Method Statement

Trade: Electricians · Generated 17/07/2026

1. Scope of works

Electrical first fix, second fix, testing and commissioning on UK construction sites.

2. Method statement

  1. Site induction and RAMS briefing signed by all operatives before work starts.
  2. Set up welfare, first-aid kit and fire point. Confirm nearest A&E.
  3. electricians team collects materials from designated laydown area — no interference with other trades' zones.
  4. Isolate, lock off and prove dead any services (electric, gas, water) in the work zone.
  5. Carry out task in accordance with method statement and manufacturer instructions.
  6. Housekeeping at end of each shift — waste segregated, walkways clear, tools tethered or stored.
  7. End-of-day sign-off with photo evidence uploaded to project record.

3. Hazards, persons at risk & control measures

HazardWho is at riskControl measures
Contact with live conductorsElectricians, apprenticesIsolate, lock off, prove dead with GS38 tester before work. Only competent persons work on installations.
Working at height (ladders, towers)All operativesPodiums preferred over ladders. Towers inspected weekly (TG20:21). Harness where fall risk >2m.
Construction dust from chasing wallsElectriciansOn-tool M-class extraction, FFP3 masks, water suppression, area cordoned.
Manual handling of consumer units, cable drumsAll operativesTeam lifts >20kg, trolleys for cable drums, staged deliveries to floor.

4. PPE required

  • Safety helmet (EN 397)
  • Safety footwear (EN ISO 20345, S3 minimum)
  • Hi-vis vest (EN ISO 20471, class 2)
  • Impact gloves (EN 388)
  • Safety glasses (EN 166)
  • Arc-flash rated gloves & face shield when live work unavoidable

5. Legislation & guidance

  • Health and Safety at Work Act 1974
  • Construction (Design and Management) Regulations 2015
  • Management of Health and Safety at Work Regulations 1999
  • Work at Height Regulations 2005
  • PUWER 1998
  • Electricity at Work Regulations 1989
  • BS 7671:2018+A2:2022

6. Approval

Prepared by (competent person)
Name / signature / date
Approved by (principal contractor)
Name / signature / date